Update 10 ( July-August, 2025)

  • Alex Byo
  • Sep 18
  • 1 min read


Significant progress has been made across the project with roofing, insulation, and all gypsum board work now complete. Painting is active throughout, Nichiha panel installation and detailing are finalized, and storefronts, doors, ceiling grids, and HVAC systems are in place. IT access points and access control rough-ins are complete, basketball goals and the scoreboard have been installed, FF&E packages are ordered, and the recording studio scope is finalized. Looking ahead, the team is preparing to finalize the permanent power connection, complete HVAC commissioning, receive and prepare the gym floor, coordinate AV and IT device installations, and begin closeout documentation to ensure inspection readiness.


Key Project Milestones: 

  • Roofing and insulation are fully complete

  • Gypsum board installation and tape/float/joint finishes are complete

  • Painting is active in all areas

  • Nichiha panel install is complete, including final trims and detailing

  • Storefront and door Fram installation is compmlete

  • Ceiling grid installation is complete in most areas, clearing the way for device and fixture installation

  • HVAC system install is complete 

  • IT access points and access control rough-ins are complete

  • Basketball goals and scoreboard are installed

  • FF&E packages have been ordered

  • Recording studio scope haș been finalized 


Key Upcoming Milestones: 

  • Finalizing permanent power connection

  • HVAC full system commissioning

  • Gym floor delivery and installation prep

  • Coordination of AV and IT device installation

  • Commencement of closeout documentation and inspection readiness

 

Change the Future today by donating to LECJF so

youth can more spaces to thrive in North Baton Rouge!