Update 10 ( July-August, 2025)
- Alex Byo
- Sep 18
- 1 min read
Significant progress has been made across the project with roofing, insulation, and all gypsum board work now complete. Painting is active throughout, Nichiha panel installation and detailing are finalized, and storefronts, doors, ceiling grids, and HVAC systems are in place. IT access points and access control rough-ins are complete, basketball goals and the scoreboard have been installed, FF&E packages are ordered, and the recording studio scope is finalized. Looking ahead, the team is preparing to finalize the permanent power connection, complete HVAC commissioning, receive and prepare the gym floor, coordinate AV and IT device installations, and begin closeout documentation to ensure inspection readiness.
Key Project Milestones:
Roofing and insulation are fully complete
Gypsum board installation and tape/float/joint finishes are complete
Painting is active in all areas
Nichiha panel install is complete, including final trims and detailing
Storefront and door Fram installation is compmlete
Ceiling grid installation is complete in most areas, clearing the way for device and fixture installation
HVAC system install is complete
IT access points and access control rough-ins are complete
Basketball goals and scoreboard are installed
FF&E packages have been ordered
Recording studio scope haș been finalized
Key Upcoming Milestones:
Finalizing permanent power connection
HVAC full system commissioning
Gym floor delivery and installation prep
Coordination of AV and IT device installation
Commencement of closeout documentation and inspection readiness