Update 9 ( June-July, 2025)
- Alex Byo
- Sep 17
- 1 min read
Construction continues to move forward with strong momentum. Two major areas have passed inspection, exterior sheathing and waterproofing are complete, and progress is evident with gym gypsum board installation, window placement, and painting underway. The transformer pad grading reset is also nearing completion. Looking ahead, the team will be addressing a leak in the backflow preventer, verifying framing spacing for the vertical Nichiha walls, coordinating deliveries for the remaining mechanical units, and finalizing both millwork submittals and dumpster enclosure drawings.
Key Project Milestones:
Two major areas have passed inspection
Exterior sheathing and waterproofing are complete
Gym gypsum board install is progressing
Window installation has commenced
Painting has commenced
Transformer pad grading reset is nearing completion
Key Upcoming Milestones:
Addressing a major leak in the backflow preventer
Verifying framing spacing for vertical Nichiha walls
Coordinating deliveries for remaining mechanical units
Finalizing millwork submittals
Finalizing dumpster enclosure drawings