Update 10 ( July-August, 2025)
Significant progress has been made across the project with roofing, insulation, and all gypsum board work now complete. Painting is active throughout, Nichiha panel installation and detailing are finalized, and storefronts, doors, ceiling grids, and HVAC systems are in place.
Sep 181 min read


Update 9 ( June-July, 2025)
Construction continues to move forward with strong momentum. Two major areas have passed inspection, exterior sheathing and waterproofing are complete, and progress is evident with gym gypsum board installation, window placement, and painting underway.
Sep 171 min read


Update 8 ( May-June, 2025)
Key Project Milestones Completed: Structural steel and all major concrete work Framing and roofing Sheathing Exterior insulation Near...
Jul 211 min read


Update 7 ( April-May, 2025)
Key Project Milestones: Structural steel and all major concrete work complete Roofing is complete except porch canopies Framing is...
May 161 min read


Update 6 ( Feb–Mar, 2025)
Key Project Milestones: Structural steel and roof decking are complete Roofing, parapets, and mechanical platforms are beign finalized...
Apr 171 min read


Update 5 (Jan – Feb, 2025)
Key Project Milestones: Structural steel erection has commenced Site utilities, including storm drainage and catch basin installation,...
Feb 161 min read


Update 4 (Dec. 2024 – Jan. 2025)
Key Project Milestones Slab pour was completed on December 23, 2024, a major milestone achieved ahead of schedule. Site utilities,...
Feb 161 min read


Update 3 (Nov. – Dec. 2024)
Key Project Milestones Foundational work – spread footings, grade beams, building pad prep – has been successfully completed. Temporary...
Dec 29, 20241 min read


Update 2 (Oct. – Nov. 2024)
Key Project Milestones Plumbing and electrical rough-ins close to completion Slab pour expected by Thanksgiving, aligning with a...
Dec 12, 20241 min read


Update 1 (Sept. – Oct. 2024)
Key Project Milestones Spread footings completed ahead of schedule Grade beam work starting earlier than expected Accelerated slab pour...
Dec 12, 20241 min read