Update 6 ( Feb–Mar, 2025)
Key Project Milestones: Structural steel and roof decking are complete Roofing, parapets, and mechanical platforms are beign finalized...
Apr 171 min read
3
0


Update 5 (Jan – Feb, 2025)
Key Project Milestones: Structural steel erection has commenced Site utilities, including storm drainage and catch basin installation,...
Feb 161 min read
12
0


Update 4 (Dec. 2024 – Jan. 2025)
Key Project Milestones Slab pour was completed on December 23, 2024, a major milestone achieved ahead of schedule. Site utilities,...
Feb 161 min read
9
0


Update 3 (Nov. – Dec. 2024)
Key Project Milestones Foundational work – spread footings, grade beams, building pad prep – has been successfully completed. Temporary...
Dec 29, 20241 min read
10
0


Update 2 (Oct. – Nov. 2024)
Key Project Milestones Plumbing and electrical rough-ins close to completion Slab pour expected by Thanksgiving, aligning with a...
Dec 12, 20241 min read
13
0


Update 1 (Sept. – Oct. 2024)
Key Project Milestones Spread footings completed ahead of schedule Grade beam work starting earlier than expected Accelerated slab pour...
Dec 12, 20241 min read
12
0