Key Project Milestones
Plumbing and electrical rough-ins close to completion
Slab pour expected by Thanksgiving, aligning with a community event to celebrate progress
Grade beam pour is completed
Entergy’s temporary power installation is nearing completion, supporting ongoing and future construction needs
Structural steel delivery scheduled for January, signaling the start of above-ground construction
Challenges & Next Steps
Utility coordination: continued focus on resolving transformer placement with Entergy
Upcoming action items:
Finalize slab pour
Secure temp power solution
Expedite approval of the IT contract
Conclusion:
Project remains on schedule with major milestones aligned to support smooth progression
AV/IT, gaming arena, and FF&E planning are advancing without budget impacts, ensuring readiness for future interior outfitting stages.