top of page

SUPPORT LECJF TODAY!

Update 4 (Oct. – Nov. 2024)




Key Project Milestones

  • Plumbing and electrical rough-ins close to completion

  • Slab pour expected by Thanksgiving, aligning with a community event to celebrate progress

  • Grade beam pour is completed

  • Entergy’s temporary power installation is nearing completion, supporting ongoing and future construction needs

  • Structural steel delivery scheduled for January, signaling the start of above-ground construction


Challenges & Next Steps

  • Utility coordination: continued focus on resolving transformer placement with Entergy

  • Upcoming action items:

    • Finalize slab pour

    • Secure temp power solution

    • Expedite approval of the IT contract


Conclusion:

  • Project remains on schedule with major milestones aligned to support smooth progression

  • AV/IT, gaming arena, and FF&E planning are advancing without budget impacts, ensuring readiness for future interior outfitting stages.

7 views0 comments

Recent Posts

See All

Comments


bottom of page