Update 7 (Jan – Feb, 2025)



Key Project Milestones:

  • Structural steel erection has commenced

  • Site utilities, including storm drainage and catch basin installation, are nearing completion

  • The transformer pad is scheduled to be poured soon, setting the stage for permanent power.

  • The kitchen and gym floor design plans were recently updated

  • FF&E and IT coordination and preparation has commenced

 

Unusual Weather Event:

  • In January, Baton Rouge experienced an unprecedented 10” of snow, a rare occurrence for the region. Fortunately, this event coincided with a period when no critical construction activities were scheduled, resulting in no delays to the project timeline.

 

Steel Beam Signing Event:

  • On February 10th, 2025, the project celebrated a successful Steel Beam Signing event. Stakeholders and team members gathered to mark this milestone, signing a designated beam. The event highlighted strong community and team engagement as the project moves upward.

 

FF&E Progress:

  • The project team is meeting with an E-Sports consultant to start detail design for the sports arena.

  • A meeting with the architect, IT consultant, and door/hardware subcontractor reviewed access control requirements, ensuring door frames and exit devices align with the submission to the general contractor.

  • A furniture consultant delivered the second round of pricing details regarding the area’s furniture specs

  • The audio consultant quotes remain on target for gym and recording studio AV installations.

 

Next steps:

  • Transformer coordination with Entergy remains ongoing

  • Completion of steel erection and utility installations

  • Advance the FF&E/IT plans and details