Key Project Milestones:
Structural steel erection has commenced
Site utilities, including storm drainage and catch basin installation, are nearing completion
The transformer pad is scheduled to be poured soon, setting the stage for permanent power.
The kitchen and gym floor design plans were recently updated
FF&E and IT coordination and preparation has commenced
Unusual Weather Event:
In January, Baton Rouge experienced an unprecedented 10” of snow, a rare occurrence for the region. Fortunately, this event coincided with a period when no critical construction activities were scheduled, resulting in no delays to the project timeline.
Steel Beam Signing Event:
On February 10th, 2025, the project celebrated a successful Steel Beam Signing event. Stakeholders and team members gathered to mark this milestone, signing a designated beam. The event highlighted strong community and team engagement as the project moves upward.
FF&E Progress:
The project team is meeting with an E-Sports consultant to start detail design for the sports arena.
A meeting with the architect, IT consultant, and door/hardware subcontractor reviewed access control requirements, ensuring door frames and exit devices align with the submission to the general contractor.
A furniture consultant delivered the second round of pricing details regarding the area’s furniture specs
The audio consultant quotes remain on target for gym and recording studio AV installations.
Next steps:
Transformer coordination with Entergy remains ongoing
Completion of steel erection and utility installations
Advance the FF&E/IT plans and details