Update 6 ( Feb–Mar, 2025)
- Alex Byo
- Apr 17
- 1 min read
Key Project Milestones:
Structural steel and roof decking are complete
Roofing, parapets, and mechanical platforms are beign finalized
Storm drainage is near completion, with one catch basin and downspout tie-ins pending
Cold-formed framing is active across the building footprint
Electrical trenching for new underground conduit began mid-April
MEP Work:
Plumbing rough-ins were completed for all restrooms and kitchen spaces
Domestic water line routing is ongoing
Electrical trenching for new underground conduit has commenced
Upcoming milestones:
Pouring of porches, mezzanine, and transformer pad
Resolution of water line routing conflicts and continuation of MEP work
Finalizing change order packages and aligning interior framing with revised FF&E and IT layouts
Beginning interior systems coordination (AV, IT, signage, lockers, etc)
Upcoming Actions:
Pour transformer pad, porches, and mezzanine
Close change order #1-6 with formal AIA documentation
Close open RFIs related to water routing and hood ventilation
Approve finish board and finalize FF&E/AV layouts based on revised framing
Coordinate infrastructure for esports and specialty equipment
Continue mechanical and electrical rough-ins following wall layout confirmation
The project remains on schedule!