Key Project Milestones:

  • Structural steel and roof decking are complete

  • Roofing, parapets, and mechanical platforms are beign finalized

  • Storm drainage is near completion, with one catch basin and downspout tie-ins pending

  • Cold-formed framing is active across the building footprint

  • Electrical trenching for new underground conduit began mid-April

 

MEP Work:

  • Plumbing rough-ins were completed for all restrooms and kitchen spaces

  • Domestic water line routing is ongoing

  • Electrical trenching for new underground conduit has commenced

 

Upcoming milestones:

  • Pouring of porches, mezzanine, and transformer pad

  • Resolution of water line routing conflicts and continuation of MEP work

  • Finalizing change order packages and aligning interior framing with revised FF&E and IT layouts

  • Beginning interior systems coordination (AV, IT, signage, lockers, etc)

 

Upcoming Actions:

  • Pour transformer pad, porches, and mezzanine

  • Close change order #1-6 with formal AIA documentation

  • Close open RFIs related to water routing and hood ventilation

  • Approve finish board and finalize FF&E/AV layouts based on revised framing

  • Coordinate infrastructure for esports and specialty equipment

  • Continue mechanical and electrical rough-ins following wall layout confirmation

 

The project remains on schedule!