Update 7 ( April-May, 2025)
- Alex Byo
- May 16
- 1 min read
Key Project Milestones:
Structural steel and all major concrete work complete
Roofing is complete except porch canopies
Framing is substantially complete
MEP, sprinkler, and IT rough-ins in progress
Sheathing underway around high walls and gym
Nichiha panel system shop drawings and delivery pending
Schedule adjustments:
Owner-directed layout revisions created follow-on coordination tasks
Contractor has implemented resequencing to regain lost time
Key upcoming milestones:
Dry-in completion
MEP and IT rough-in inspections
Transition to gypsum board and ceilings