Update 7 ( April-May, 2025)

  • Alex Byo
  • May 16
  • 1 min read



Key Project Milestones:

  • Structural steel and all major concrete work complete

  • Roofing is complete except porch canopies

  • Framing is substantially complete

  • MEP, sprinkler, and IT rough-ins in progress

  • Sheathing underway around high walls and gym

  • Nichiha panel system shop drawings and delivery pending

 

Schedule adjustments:

  • Owner-directed layout revisions created follow-on coordination tasks

  • Contractor has implemented resequencing to regain lost time

 

Key upcoming milestones:

  • Dry-in completion

  • MEP and IT rough-in inspections

  • Transition to gypsum board and ceilings