Update 8 ( May-June, 2025)
- Alex Byo
- Jul 21
- 1 min read
Updated: Sep 18
Key Project Milestones
Completed:
Structural steel and all major concrete work
Framing and roofing
Sheathing
Exterior insulation
Near complete:
MEP, sprinkler, and IT rough-ins (inspection underway)
Wireless access point rough-ins
Commencing:
Security camera rough-in
Pending
Nichiha panel system shop drawings and delivery
HVAC equipment delivered and being prepared for installation
Ongoing
Exterior grading to move into find grading, prepping for perimeter sidewalk installation
Design Updates
Dumpster pad: design coordination ongoing with BREC. Final derective to come in future ASI; this item is not critical.
Basketball court: logo and color scheme needs to be decided on soon.
Key Upcoming Milestones:
Furniture layout & pricing to be completed
Final determination on locker locations inside of building and use