Update 1 (Sept. – Oct. 2024)

  • Writer: Erik Sampson
    Erik Sampson
  • Dec 12, 2024
  • 1 min read

Updated: Mar 21



Key Project Milestones

  • Spread footings completed ahead of schedule

  • Grade beam work starting earlier than expected

  • Accelerated slab pour targeted for November to avoid rain delays


Key Achievements

  • Soil issue resolution:

    • Proactive soil replacement kept schedule on track

    • Cost-effective solution with minimal impact on budget

  • Coordination & Efficiency:

    • Early completion of spread footings allowed for smoother progress


Conclusion & Action Points

  • Strong position: the project is currently ahead of schedule

  • Focus areas:

    • Accelerate key tasks before the rainy season

    • Incorporate upcoming ASI#3 to capture needed design adjustments

    • Shift back to FF&E refinement and coordination