Key Project Milestones
Foundational work – spread footings, grade beams, building pad prep – has been successfully completed.
Temporary power is active on-site.
Gravel placement and vapor barrier installation are underway.
Key design updates include kitchen revisions, gym floor box adjustments, and early Murphy Stage coordination.
Key Achievements
FF&E layouts are being refined.
Audio equipment quotes align with budget expectations, supporting AV installations in the gym and recording studio.
Currently pending e-sports build-out quote and design.
Conclusion & Action Points
The project remains on track.
Upcoming milestones include the slab pour on December 23, 2024 and structural steel installation in January 2025.
Work continues on permanent power and the transformer.