Update 5 (Nov. – Dec. 2024)






Key Project Milestones

  • Foundational work – spread footings, grade beams, building pad prep – has been successfully completed.

  • Temporary power is active on-site.

  • Gravel placement and vapor barrier installation are underway.

  • Key design updates include kitchen revisions, gym floor box adjustments, and early Murphy Stage coordination.

 

Key Achievements

  • FF&E layouts are being refined.

  • Audio equipment quotes align with budget expectations, supporting AV installations in the gym and recording studio.

  • Currently pending e-sports build-out quote and design.

 

Conclusion & Action Points

  • The project remains on track.

  • Upcoming milestones include the slab pour on December 23, 2024 and structural steel installation in January 2025.

  • Work continues on permanent power and the transformer.

 